2013-11 - November - Cation & Anion Glucose demineralisation unit

A new Cation & Anion glucose demineralisation unit with a capacity of 40 m³/h has been designed and constructed by PuriTech.

The detailled engineering starting from PFD's & P&ID's with all datasheets & vessel drawings have been engineered by our PuriTech engineers.

    

Mechanical installation on site has started from May 2013 and was finished in September.

Beginning of next year, resin filling and hydropressure testing will be executed.

The start-up of the complete system is scheduled for Q1 - 2014.